Submit Your Suggestions for Viewpoint Team

TEAM needs to push into the Vista records the "actual dates" submittal items were Received from Sub, Sent to AOR, Received from AOR, Returned to Sub.

The "Actual" dates are important pieces of information required for several of our custom reports which are used extensively in Vista.

The reporting feature in TEAM is not sophisticated enough to provide a professional level report which is required by our standards.

Currently our project engineers are having to enter the information in manually into Vista which takes a considerable amount of time.

  • Joseph Miller
  • Aug 8 2018
  • Future consideration
Company PENTA
Job Title / Role Project Executive / Director of Training
I need it... Yesterday...Come on already
  • Attach files
  • veronica mcallister commented
    December 15, 2022 19:02

    Yes please!!!!!!!!!!!! This has been an issue way too long!


  • Carisa Buckley commented
    May 31, 2022 15:29

    This should have been done from the start. This is causing double work for our staff, and should be an automatic flow from Team to Vista. Please implement ASAP!

  • Kim Givens commented
    July 21, 2021 20:07

    AGREED. Having to work submittal information in 2 different places makes no sense.

  • James Fencil commented
    February 16, 2021 21:06

    Yes please!!!!!!!!!!!!

  • Christie Holzschuh commented
    November 09, 2020 21:38

    This is a huge issue that should be addressed as soon as possible. The data writing back to Vista is 100% useless without an approval or rejection date available. Please review and implement ASAP.

  • Guest commented
    May 26, 2020 19:44

    Huge issue for us as well. We had custom reports created for our logs in Vista and with the incomplete data from TEAM these reports are useless unless I manually update each submittal once something has been updated in TEAM. Also, we use the notifier function in Vista for some of our older projects. Since this notifier is turned on Vista is attempting to send our subs notices that submittals are due when in fact they have already been completed its just that the info from TEAM has not pushed to Vista. Huge source of confusion for our subs and hard for me to remember to update after each change comes in TEAM to keep these notices from going out of Vista.

  • Guest commented
    December 27, 2018 02:03

    This is something our firm needs as well, part of normal shop drawing processing to track where the submittal has moved with these critical dates for record purposes.

  • Guest commented
    August 31, 2018 12:57

    This is a huge issue for our system as well.  This change would be excellent.

Dear Viewpoint Suggestion Box contributor;

We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs. Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.

1515 SE Water Avenue, Suite 300, Portland, OR 97214 |  800.333.3197  | Contact Us | Terms of Use | Privacy | Support Policies

© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.