Approval Hierarchy with Due Dates

We are having a lot of push back from Architects receiving too many notifications because of one additional approver not approving/rejecting.  The Architect cannot finalize the Submittal until all the additional approvers have commented.  It would be very helpful if we could have a hierarchy on the approvers:

1.  Structural Jane Doe - Due Date - May 11
2.  Electrical John Smith - Due Date - May 13

3.  Architect (primary) Alex Smith - Due Date - May 15

When the Submittal is sent for approval, all will receive separate emails with their due dates.  In the example above, John Smith cannot approve/reject until Jane Doe does and on May 12, Jane gets an overdue email.  Once Jane Doe approves/rejects, both John Smith and Alex Smith get a notification with Jane Doe's comment.  Then the ball in court moves to John Smith and so on.

As of now, our primary consultant is being tasked with getting all the additional approvers to update the submittal, but that's not their job and they are receiving all of the notifications.  

  • Mercedes Green
  • May 9 2018
Company Skygrid Construction Inc.
Job Title / Role Technology Strategist
I need it... 3 months
  • Attach files
  • Mercedes Green commented
    August 12, 2021 15:39

    3+ years....Not even a "future consideration" yet we have been complaining about this for 4 years now.

  • Mercedes Green commented
    December 01, 2020 20:55

    Almost 1 year later from my last comment and still no updates, not even if it's planned. We need this much more than ANY of the modules being created.


    Can we pay extra to have this customization done? If so, please contact me with a quote. We have more and more projects moving to Procore.

  • Carlos Riobo commented
    April 20, 2020 16:17
  • Michael Krug commented
    May 15, 2019 19:01

    Please make this a reality!

  • Eric Elfner commented
    February 05, 2019 16:09

    We have another suggestion that we should be able to make additional approvers required (right now the final approver can trump everyone else and approve it even if additional approvers haven't.)  But at a team workshop this week, it would be even better if they could be required and hierarchical so that it moves through approvers and sends notifications.  I think it should be flexible so users can designate approver order, with the final approver changing the status to Approved, but not unless all required approvals have.

  • Mercedes Green commented
    December 18, 2018 20:32

    We are getting so many complaints about this.  I know it's only 2 votes but it's this or our consultants stop using TEAM completely.  

Dear Viewpoint Suggestion Box contributor;

We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs. Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.

1515 SE Water Avenue, Suite 300, Portland, OR 97214 |  800.333.3197  | Contact Us | Terms of Use | Privacy | Support Policies

© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.