There is a date field for when the submittal/RFI is due back from the architect, but it would be helpful if a date autopopulated when you received the actual response back from the architect. Date due from the architect and actual date returned are different and both are relative for tracking purposes.
Company | Sachse Construction |
I need it... | Yesterday...Come on already |
Dear Viewpoint Suggestion Box contributor;
We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs.
Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.
© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.
I'm going to go ahead and close this one out - we'll track the request for Vista write-back on this suggestion: https://viewpoint.aha.io/ideas/VPT-I-164
We added the the actual state change dates in March but we have the Vista write back as a separate feature that is yet to be done.
Please include this into Vista writeback for reporting ASAP.
Looks like you have to activate the columns from the column configuration to see these actual dates. It does not appear the due dates change though based on Sbmtl date of process as related to days setup in Project Settings.
Would also be good to see these dates in the Sbmtl window when in that sbmtl. Looks like we are getting there but not quite, would you all agree?
If this was added to the version released on Monday, why is it not in the release notes? This is from 6.15.07: The Vista™ by Viewpoint 6.15.07 release contains bug fixes only; there are no enhancements included with this release. How are we to know what's changed without a change log?
FYI this was added just this Monday night!
Voted on this, but it relates to this item I created almost a year ago: https://team.ideas.aha.io/ideas/MVPM-I-111
Would need Date received from sub also
Would also be helpful for tracking and reporting purposes if we had the following date fields auto-populate:
- Date sent to architect
- Date sent to the subcontractor (submitter)
- Actual date delivered (this would have to be a manual entry)