When a work item, Submittal, RFI, and Issue, is closed in Team, the item remains open in Vista. In Keystyles, Issues are shown as open until they are closed in Vista. Could this be changed so once an item is closed it Team, the item will close in Vista.
Company | Quandel Construction |
I need it... | Yesterday...Come on already |
Dear Viewpoint Suggestion Box contributor;
We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs.
Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.
© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.
When exactly is this supposed to change?!
The way it is right now is not a very lean process. Taking extra steps goes against everything VP is selling!
It's supposed to change. Most of ours do in all our projects but still have issues where the odd one is not update in Vista so our reports are all out of sync.
What we did is select all the RFIs, do mass edit (say add a internal note), unmark the notify and that should push the update to Vista. Try it on a couple to start.
Yes, RFIs, and Issues the status does not change. With RFIs, the status does not show, Issues stays as open. With submittals, the status will change but will not close. Even with a final code type status, the line will still highlight to show the line overdue. To close the submittal Vista, you have to change the status to back to open, then change it back to the final status for the submittal to close.
I just submitted a case to Clearview about what I think is the same issue. When I close an RFI in Team, the State turns to "Closed" but the Status remains "Open." That the same thing happening to you?