When a project is working day and night shift we need a way to capture weather data for more than the 3 available time slots...for instance 6pm, 11pm, 4am
Company | Primoris Services Corporation |
Job Title / Role | Project Controls Manager |
I need it... | 3 months |
Dear Viewpoint Suggestion Box contributor;
We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs.
Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.
© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.
per-log instead of per-project - along those lines per log be able to set weather capture. One project with six different location sites. Would be helpful to set weather per location.
If we can have a selection for shift for daily report that would allow 3 time slots per shift
Rob Reynolds
Direct: (225) 442-6352
Cell: (256) 810-1138
rreynolds@prim.com
If you go to Project Settings > Daily Logs you can customize your weather capture times. The settings are project-wide though - it sounds like for the day shift/night shift use case we would need to have times customizable per-log instead of per-project - is that right?